Sand
Layers Should Not Be Placed Between
Polyethylene Vapor Barriers and Concrete Floor Slabs
by Joseph Lstiburek, Ph.D., P. Eng.
Excess slab moisture intrusion problems resulting in flooring
failures, mold growth and other microbial contamination problems
are typically due to sand layers located between polyethylene
vapor barriers and concrete floor slabs.
The sand layers become reservoirs for water in the liquid state
(bulk water) that enters the sand layers by gravity flow from
the top, sides and bottom of the sand layers (Figure 1). The liquid
water is both held in the sand layers and redistributed within
the sand layers by capillarity (Figure 2). Additionally, due to
these capillary forces, the liquid water is incapable of draining
out of the sand layers. The only mechanism of drying of the sand
layers is upwards through the concrete slabs by vapor diffusion
and capillary draw (Figure 3).


There is no barrier or protection for the upward moisture flow
through the concrete slabs from the wetted sand layers. The intended
protection for upward moisture flow from below grade are the polyethylene
vapor barriers, but this intended moisture protection has been
rendered ineffective by the gravity flow wetting mechanism that
has saturated the sand layers that are located above the polyethylene
vapor barriers.
The moisture flow upwards through the concrete slabs by vapor
diffusion and capillary transmission passes through the top surface
of the concrete slabs as well as through floor surface treatments
and leads to mold and other microbial contamination problems.
The rate of wetting of the sand layers by the gravity flow
wetting mechanism is several orders of magnitude greater than
the rate of drying of the sand layers by the vapor diffusion and
capillary transmission drying mechanism. The sand layers become
water reservoirs that continually supply water for the upward
flow through the concrete slabs by vapor diffusion and capillary
transmission.
Picture the sand layers as "blotter paper" that once
wetted do not let water drain out of them. The only method of
drying available to the "blotter paper" is evaporation.
In the case of the sand layers the only method of "evaporation"
is upwards through the concrete slabs due to the presence of the
polyethylene vapor barrier under the sand layers.
Concrete slabs should be placed in direct contact with polyethylene
vapor barriers. A sand layer should not be installed between concrete
slabs and polyethylene vapor barriers.
Where concrete slabs are in direct contact with polyethylene
vapor barriers a reservoir is not created if rainfall occurs during
the construction process and penetrates the slab, or if wet curing
is used. Additionally, wet concrete cutting operations, cracks
in slabs, gaps and penetrations in the polyethylene vapor barrier
coupled with cleaning, water testing, ground water migration or
irrigation do not affect slab moisture transmission if a reservoir
is absent or cannot be created between the polyethylene and the
concrete slab.
When concrete slabs are cast directly over polyethylene vapor
barriers the concrete water-to-cement (w/c) ratio must be correctly
specified in order to control bleed water and plastic shrinkage
cracking. Bleed water will not be present if the w/c ratio is
below 0.5 and plastic shrinkage cracking becomes negligible when
the w/c ratio is below the range of 0.48 to 0.45. Differential
drying and slab curl are controlled with either a curing compound
or a temporary covering of plastic sheeting.
Concrete slabs with a w/c ratio of 0.45 or less should be placed
directly on a polyethylene vapor barrier coupled with a curing
compound or a temporary plastic sheeting slab covering in order
to avoid problems.
The following 4 reasons are generally cited for using a sand
layer over polyethylene vapor barriers is as follows:
1. The sand layer controls bleed water with high w/c ratio
concrete slabs
2. The sand layer reduces curl with high w/c ratio concrete slabs
when top-side curing is not controlled
3. The sand layer reduces plastic shrinkage cracking with high
w/c ratio concrete slabs
4. The sand layer protects the polyethylene vapor barrier from
punctures
The first three reasons are based on sound technical arguments.
However, each of the first three are based on the condition that
the sand layer be prevented from getting wet during the construction
process and beyond and are typically associated with floor slabs
that are placed "after the building is enclosed and the roof
is watertight." Additionally, the first three are based on
the condition that wet curing such as ponding or continuous sprinkling
will not occur or that joint sawing using wet methods or power
washing will not occur. The first three are also conditional on
slab and foundation designs that will not be sensitive to ground
water wetting from local water tables and local irrigation.
In the case of exposed slab construction, the first three reasons
are rendered moot since the conditions for their use are not met
nor can they be met. Accordingly, a sand layer should not
be specified.
The fourth reason, "puncture protection", is based
on incorrect physics. A sand layer is not necessary to protect
polyethylene vapor barriers. Vapor diffusion is a direct function
of surface area. Rips, holes, tears and punctures in sheet polyethylene
vapor barriers constitute a very small surface area of vapor transmission
compared to the total floor slab area. If 95 percent of the surface
area of the slab is protected by a vapor barrier, then that vapor
barrier is 95 percent effective. This holds true only if air flow
or air leakage is not occurring through the vapor barrier. Where
concrete is in direct contact with the polyethylene vapor barrier
this is the case. Air flow is not occurring. The concrete slab
is an "air-barrier" and the polyethylene is the "vapor
barrier" and an effective vapor barrier even if the
polyethylene has numerous punctures.
In the case of exposed slab construction there is no justification
for the use of a sand layer between the polyethylene vapor barrier
and the concrete slabs.
The specification of a sand layer over a polyethylene vapor
barrier is typically directly responsible for flooring failures,
mold and microbial contamination problems.
|