What's New

About BSC

Building America

Technical Resources

FAQ

Seminars & Workshops

Joe's Top Ten

Links

Home

Designs That Work
Very Cold Climate

The Basic House - Building Enclosure

A fundamental part of durable, energy efficient, and sustainable construction is the design of the building enclosure. Water managed, thermally efficient, and leak free building enclosures, while providing for durable structures and reducing energy consumption, also allow us to maintain better control of our interior environmental conditions. In order to achieve this, the various components of the building enclosure (roofs, walls, foundations, windows and doors) must be designed to fulfill their individual requirements. However, these components must also be tied together in such a way as to create a complete system to control rain water, air leakage, vapor migration, and thermal transfer. In addition, the systems should be economical while still being robust enough to handle the various climate loads that are imposed on them.

Rain water infiltration is the largest source of material deterioration in buildings. The control of rain water is best achieved if some simple principles of drainage are followed. The fundamental design looks to create a means to drain water off the building, out of the assemblies and components, and away from the building. The design uses a strategy referred to as a rain screen approach. In a rain screen approach, the exterior primary plane of water shedding (cladding, shingles, metal roofing, etc) is not relied upon to be completely perfect. A secondary drainage plane (usually a housewrap or taped insulating sheathing) is installed behind the main exterior water shedding surface. This drainage plane in combination with flashing details allow any water that may penetrate through the exterior water shedding plane to drain back out to the exterior.


Figure 5: Diagram of Drainage

After liquid water intrusion, air leakage is the second most common mechanism for depositing moisture in wall assemblies. Air leakage occurs due to air pressure differentials causing air to flow through or within the building assembly. In order to control air leakage a continuous plane of air seal must be created. This air seal must be continuous not only for each building assembly, but at the connection between adjoining building assemblies. Uncontrolled air leakage can also impact the energy efficiency of the building as infiltrating air will need to be conditioned or through the loss of exfiltrating conditioned air. The Building America goal is to achieve an infiltration rate equivalent to 2.5 square inches per 100 square feet of building enclosure area. Creating a continuous air seal is possible; however, special attention is often needed at transition details between different assemblies and systems.


Figure 6: Moisture transport comparison

Vapor transport through diffusion can be a benefit or a detriment. In some circumstances, vapor diffusing into a wall assembly can condense and accumulate resulting in problems with material deterioration. On the other hand, vapor diffusion can also be used as a drying mechanism that will allow assemblies to dry to either the exterior or the interior or both. In general, the vapor control strategy used should maximize the drying potential of the assembly while minimizing the potential for wetting. With vapor diffusion being affected by both permeability of building components and temperature gradients across assemblies, the vapor control strategy is often related to, and integrated in, the insulation system design as well. For hot humid climates such as this, the assemblies are designed to prevent hot humid exterior air from diffusing into the assemblies, while allowing the assemblies to dry to the interior.

To control thermal transfer, the intention is to maximizing the thermal insulating value of all 6 sides of the building enclosure to levels that are suited for the climate zone while not becoming cost prohibitive. The thermal transfer if primarily managed by the insulation type, thickness, and location; however other aspects such as framing design, and window U-value and Solar Heat Gain Coefficient (SHGC) are important as well.

To keep the cost of the systems down, reducing material use in the assemblies and material waste on the project is important. This can be done by efficient layout of the house plan and efficient use of materials. Reducing material use must be done in such a way however so as not to affect the robustness or structural integrity of the building. Provisions to maintain adequate wind and seismic resistance must always be incorporated into the design.

Roof Design

The roof is designed with asphalt shingle installed over a layer of building paper on OSB sheathing. Below the OSB sheathing is a 4 inch ventilation space created by installing 2x4 studs on edge on a 4 inch wide strip of ½ inch plywood that is screwed through to the rafters. This ventilation space will help remove any heat loss through the insulation to prevent problems with ice damming on the roof eaves.


Figure 7: Roof Construction Section

In addition the ventilation space will help to dry any moisture that may penetrate past the exterior shingles. Below the insulation is a drainage plane created by the housewrap, this is the final layer of protection against any water intrusion into the assembly and must be continuous. The overhangs from the roof are designed to extend a minimum of 2 feet from the exterior wall. This amount of overhang will provide protection for the wall elements such as windows and doors that are traditionally common sources of water leakage. With the overhangs preventing the wall systems from getting wet, the risk of water intrusion through these elements is greatly reduced.


Figure 8: Roof Drainage

The attic is designed as an unvented attic. With unvented attics such as this, the plane of air tightness is located at the plane of roof and not at the ceiling plane as is common with vented attic designs. While the attic is not vented to the exterior, soffit and ridge vents are installed to vent the gap between the insulation and the exterior roof sheathing. The air tightness for this assembly is provided by the housewrap sandwiched between the rigid insulation and the interior layer of roof sheathing. In order to maintain the continuity of the air seal between the roof and the wall the housewrap must be continuous from the roof down onto the wall with all the joints taped and sealed.


Figure 9: Roof Air Barrier

With all of the insulation installed to the exterior of the structure common problems of condensation within the structure are eliminated. The location of the insulation moves the dew point of the assembly exterior of the structure and in a location where the materials used in the construction are resistant to moisture damage. If condensation were to occur, it is exterior of the drainage plane of the assembly and the moisture would be able to drain out to the exterior.


Figure 10: Roof Vapor Management

The thermal resistance of the assembly is provided by the 12 inches of rigid EPS insulation installed to the exterior of the structure. With cavity insulation, the framing members (studs, top and bottom plates, window headers, etc) are thermal bridges through the insulating layer. These thermal bridges can reduce the rated R-value of the insulation upwards of 35% to 40%. This means that a 2x6 stud wall with a rated R-19 fiberglass batt will in reality have an effective R-value of around R-13 for the entire assembly. For this design, since the insulation is installed exterior of the structure, concerns with thermal bridging of the framing members are essentially eliminated. This means that close to the entire rated insulating value of the insulation will be effective in providing thermal resistance. 12 inches of rigid EPS installed to the exterior of the structure will have an effective R-value of R-42.


Figure 11: Roof Thermal Resistance

Wall Design

The wall water management system is designed with a ventilated and drained cavity behind the wood siding. The wood is held off of the rigid insulation with 1x4 furring strips. These furring strips provide for an air gap that acts both as a drainage gap and ventilation gap. This allows any water that penetrates past the siding to drain to the exterior and allows for air flow behind the cladding to help with drying of the cavity. In order to protect the wood from moisture related problems, the wood siding should be back primed (primed on all 6 sides including end cuts) with an oil based primer and painted with two coats of latex paint. The actual drainage plane for the assembly is the housewrap behind the rigid insulation. Likely, any water penetrating past the cladding will drain down the exterior face of the rigid insulation, however, some water may still get past at the joints in the rigid insulation boards. For this reason it is still important that the continuity and integrity of the housewrap drainage plane be maintained. All flashings should be tied back to this plane and shingle lapped into the housewrap.


Figure 12: Wall Drainage

The air tightness for this assembly is provided by the housewrap sandwiched between the rigid insulation and treated OSB sheathing. The continuity is maintained at the top by ensuring continuity with the roof housewrap. At the connection to the floor, the housewrap is continuous past the rim joist and sealed to the OSB sheathing. The air seal is then maintained by sealing the OSB sheathing to the rim joist of the floor assembly.


Figure 13: Wall Air Barrier

With all of the insulation installed to the exterior of the structure common problems of condensation within the structure are eliminated. The location of the insulation moves the dew point of the assembly exterior of the structure and in a location where the materials used in the construction are resistant to moisture damage. If condensation were to occur, it is exterior of the drainage plane of the assembly and the moisture would be able to drain out at the bottom of the wall assembly to the exterior.


Figure 14: Wall Vapor Management

The thermal resistance of the assembly is provided by the 8 inches of rigid EPS installed to the exterior of the structure. As mentioned in the roof design section, with cavity insulation, the framing members can reduce the rated R-value of the insulation upwards of 35% to 40%. This means that a 2x6 stud wall with a rated R-19 fiberglass batt will in reality have an effective R-value of around R-13 for the entire assembly. For this design 8 inches of rigid EPS installed to the exterior of the structure will have an effective R-value of R-28.


Figure 15: Wall Thermal Resistance

The layout of the walls on the floor plan follows a 24 inch grid. This 24 inch grid makes use of standard material dimensions for sheathing and insulation products. This reduces cutting and material waste on site. Following this, the walls are designed with the use of advanced framing techniques (advanced framing uses 2x4 studs at 24 inches on center, single top plates, two stud corners, and headers over windows only on load bearing walls).

The lateral load resistance is provided by completely sheathing the wall area with OSB sheathing.

Foundation Design

The foundation is designed as a pier foundation with the floor elevated off the ground. This foundation allows for more construction options in areas where the ground is frozen for long period of the year and uneven rocky conditions make creating level footprints more difficult. In addition, the open nature of the foundation will allow for snow to blow through, preventing severe drifting of snow up against the house.


Figure 16: Foundation Drainage

The air tightness for this assembly is provided by the housewrap sandwiched between the rigid insulation and the OSB subfloor. At the connection to the wall, the housewrap is draped over the exterior of the rim joist and sealed to the back of the wall OSB sheathing.


Figure 17: Foundation Air Barrier

The insulation is installed above the framing structure of the floor. The assembly is designed to dry to both the interior and the exterior. The EPS insulation is semi permeable and will limit the amount of moisture that is able to diffuse into the assembly. Any moisture that does will be able to dry to the exterior.


Figure 18: Foundation Vapor Management

Similar to the wall assembly, the thermal resistance of the assembly is provided by the 9 3/8 inches of rigid EPS insulation installed in the floor structure. For this design 9 3/8 inches of rigid EPS installed to the underside of the structure will have an effective R-value of R-33.


Figure 19: Foundation Thermal Resistance

For this design, the strength of the floor structure is provided by the EPS insulation sandwiched between two layers of OSB sheathing. Load from the exterior walls is transferred through the floor structure by the double 2x10 perimeter rim joist. At interior partition walls additional 2x10 floor joist are installed to transfer the load to the pier foundation. This reduces the amount of framing that is traditionally required in a standard floor assembly while also providing for superior thermal resistance.

Windows and Doors

The window and door installations are designed to be drained systems. A pan flashing is installed below every window and door to direct any water that may leak through or around the window back out to the exterior. The window is located in the wall so that the flanges of the window are at the same plane as the housewrap drainage plane behind the rigid insulation. The nailing flanges of the window are sealed with a membrane flashing on the jambs and head of the window. The sill is left open to allow the water to drain out. At the head, the housewrap should be lapped over the membrane flashing to prevent a reverse flashing from being created (Please refer to window installation sequence details on drawing A-7).


Figure 20: Window Pan Flashing

The continuity of the air barrier is maintained by installing a bead of non-expanding urethane foam between the window frame and the rough opening on all four sides of the window. The foam is installed from the interior prior to the installation of the interior trim. The foam should also be closer to the interior so as not to block drainage of the pan flashing at the sill of the window.


Figure 21: Window Air Barrier Continuity

The thermal resistance of the window is provided by the overall U-value of the window assembly as well as the Solar Heat Gain Coefficient. The values used for this home were a U-value of 0.33 and an SHGC of 0.3 and are representative of what is available on the market. For very cold climates, it is recommended to minimize the overall U-value of the windows for all orientations, however having a higher SHGC on the South elevation can be of some benefit through increased solar gain in the winter months offsetting the heating loads for the house. While this is a good idea in theory, finding a window that has a low U-value and a high SHGC can be difficult. In general windows with lower U-values also have lower SHGC’s.

Other Penetrations

There are many other penetrations that are often overlooked in the design of houses. These are from dryer vents, bathroom exhaust fans, exterior electrical outlets, exterior lights, gas lines, etc. These penetrations must be designed into the water management system. Pipe penetrations such as bathroom exhaust vents or dryer vents should be stripped into the drainage plane with membrane flashing. Where the electrical box are installed flush with or penetrates through the drainage plane, the box should be stripped in with a membrane flashing to create a flanged seal to the drainage plane. Alternately there are products available on the market that have flanges as part of the electrical box or mechanical vent. With these products the flanges can be then integrated into the drainage plane.

All penetrations through the plane of air tightness should be sealed with caulking or spray foam in order to maintain the continuity of the air barrier.

These penetrations are thermal bridges. In order to minimize the effect of the thermal bridging, the insulation should be installed as close as possible to the penetration to minimize the impact of the disruption of the insulating layer.

Energy Model Results

The results of the building enclosure upgrades represented a reduction in energy consumption of 23.7% when compared to the energy consumption of the Building America Benchmark house design.

Building Science Consulting
70 Main Street, Westford, MA 01886
978.589.5100
Contact Us