Designs That Work
Hot-Dry / Mixed-Dry Climate: Sacramento Profile
PDF
Version
Cross Section

Construction Recommendations
- Foundation: Post-tentioned slab-on-grade
- Above Grade Wall: Wood frame
- Cladding (1st floor): Fiber cement siding
- Cladding (2nd floor): Stucco
- Attic: Unconditioned
- Roof: Tile
Building Science Notes
- Ducts in conditioned space - This building profile is
designed to accommodate HVAC equipment and ducts in the living space.
Specifically, the duct system is a blow up/blow down configuration
located in either the second floor framing or an extensive network of
dropped soffits. Use of advanced framing and opened web floor trusses is
a good fit here, with the duct system in the floor trusses.
Click here for
more information.

Figure 10 |
- Air sealing details at transitions – Air sealing can be
particularly difficult, but no less important, at assembly transitions
such as band joists and between attached garages and living spaces.
These are discussed below because they have proven to be a consistent
challenge for high performance production builders.
- Band joists – Continuity of an exterior air barrier can be
maintained at the band joist with sealed or taped housewrap or rigid
foam insulation. Continuity of an interior air barrier can be
maintained through a combination of cut foam blocks and sealant/caulk,
rigid draftstopping (wood blocking) and sealant/caulk, or spray foam.
Note that neither cellulose nor fiberglass (batt or blown) can be used
for the air barrier. The air barrier detail on second-story band
joists is important because it is inaccessible (covered by
structural/finish floor and ceiling finish) after construction. The
air barrier/thermal barrier detail is important on ground floor band
joists because of the thermal bridge that can occur at the top of
crawlspace foundation walls (as the result of the air barrier and
thermal barrier moving from the outside to the inside of the building
enclosure and termite inspection zones located at the top of basement
and crawlspace foundation walls). Note that while fiberglass batts
fulfill the requirement for protection from ignition in the open band
joists, fiberglass batt material by itself cannot maintain the air
barrier.
- Attached garages – The building enclosure surfaces shared between
conditioned space and an unconditioned garage must have a continuous
air barrier. See Figure 10 and
Air Sealing
for details in terms of using sealants and rigid insulation to create
a continuous air barrier between the attached garage and living space.
- Drying mechanisms – In any climate, vapor control is based on
the relationships among the following: the permeability of wall
components, the type of cladding (reservoir or non-reservoir), the
presence/lack/nature of an air space, and the magnitude/duration of the
vapor drive (based on the relationship between the exterior and interior
moisture content and temperature differences). The type of sheathing and
housewrap used in any wall assembly must be based on an understanding of
these inter-relationships. See “Insulations,
Sheathings, and Vapor Diffusion Retarders” for more information. This
wall assembly permits drying to the interior and limited drying to the
exterior (vapor semi-permeable XPS insulation on the second story, OSB
on the first story).
- Drainage plane, air barrier, and vapor control – The drainage
plane in this wall assembly is the layer of building paper on both
stories. The air barrier is the interior gypsum board installed using
the Airtight Drywall approach (see Air Sealing Details). The wall and
roof assemblies in this building are “flow-through” assemblies, with
some degree of vapor permeability in all components of the wall and
roof. This bi-directional drying is the preferred approach in Mixed-Dry
climates. The most common exterior rigid insulation used in this
assembly is expanded polystyrene (EPS), a semi-vapor permeable
sheathing.
- Rough opening flashing – Window and door flashing details are
wall assembly or cladding specific and depend on whether the windows are
installed before or after the drainage plane. Refer to the EEBA Water
Management Guide for more information at the
EEBA Bookstore.
- Advanced framing – This wall assembly employs all of the
advanced framing methods, including structural bracing rather than
sheathing on the first floor. For advanced framing details, see
Using Wood
Efficiently. For information on the inset shear panel developed for
a comprehensive approach to advanced framing in seismic regions, see
Figure 11 and
Design Guidance for Inset Wood Shear Panels.

Figure 11
|
- Framing on slabs – Installing a capillary break between the
sill plate and a concrete slab on all walls—exterior, interior,
partition—is good practice. A closed cell foam sill sealer or gasket
works well. Alternatively, a strip of sheet polyethylene can be used.
This isolates the framing from any source of moisture that may be either
in or on the concrete slab (and using sill sealer on all walls maintains
the same wall height).
- Soil gas ventilation – The sub-slab to roof vent system
handles conditions that are difficult if not impossible to assess prior
to completion of the structure—resultant confined concentrations of
air-borne radon, soil treatments (termiticides, pesticides) methane,
etc. The cost of this “ounce” of prevention is well balanced against the
cost of the “pound” of cure.
- Sub-slab stone bed - The four-inch deep, 3/4-inch stone bed
functions as a granular capillary break, a drainage pad, and a sub-slab
air pressure field extender for the soil gas ventilation system. Without
it, a soil gas ventilation system is not practically possible and the
only capillary break between the slab and ground is the polyethylene
vapor barrier.
- Thermal barrier - The heat loss through the slab perimeter is
significant enough to warrant slab-edge insulation.
- Vented attic – Soffit and ridge vents provide more effective
attic ventilation than gable-end vents. Gable exhaust fans do not
provide effective attic ventilation. They are generally
temperature-controlled, when relative humidity is often the condition
that requires higher ventilation rates. They can also depressurize the
house causing loss of conditioned air. Generally, the area of the gable
and soffit vents, combined with the leakage of the attic ceiling, is
such that the fan pulls air not just from the exterior vent but from the
conditioned space below.
Climate Specific Details
- Mechanical systems
- Heating – Sealed combustion hot air furnace. Sealed combustion means
that the unit can be located within the conditioned space with no
compromise in indoor air quality or combustion safety.
- Cooling - Evaporative cooling is prevalent in Mixed-Dry Climates. We
recommend refrigerant cooling in high performance homes in this climate
region for three reasons:
- Refrigerant cooling permits year-round controlled ventilation;
evaporative cooling does not.
- Evaporative cooling can be prone to moisture and indoor air
quality problems without frequent and diligent system maintenance,
refrigerant cooling is not.
- While there can be a slight energy penalty with refrigerant
cooling in comparison to evaporative, this penalty must be balanced
against the year-round comfort provided by refrigerant cooling
(evaporative cooling has difficulty supplying comfort in high humidity
situations) and the substantial water savings associated with
refrigerant cooling (a growing issue in mixed-dry climates).
Follow appropriate sizing procedures. See the following for more
detailed information:
Cooling System Sizing Pro.
- Ducting - Single return requires transfer grilles to provide path
and avoid pressurizing bedrooms, as shown in the figures at right.
Appropriate sizing for ducts, including these pressure relief methods,
can be found see Figures 12a-d or go to
Cooling System Sizing Pro.

Figure 12a-d
- Controlled mechanical ventilation - Intermittent
central-fan-integrated supply, designed to ASHRAE 62.2P rate, with fan
cycling controls set to operate the central air handler as much as 33% of
the time, but not less than 25 % of the time, occurring within at least
every three hours to provide ventilation air distribution and whole-house
averaging of air quality and comfort conditions (installed cost: $125 to
$150). Include a normally-closed motorized damper in the outside duct with
the AirCycler FRV control (installed cost: $50 to $60). See Figures
13, 14 and 15.

Figure 13 |

Figure 14 |

Figure 15 - Interior Closet Configuration
|
- Termite management – Termites are best managed with a
three-pronged approach that deals with the three things termites
need—cover from sunlight, moisture, and food (wood or paper):
- Reduced cover – Keep plantings 3 feet away from the building
perimeter, thin the ground cover (wood mulch or pea stone) to no more
than two inches depth for the first 18 inches around the building, and
maintain any termite inspection zone on the exterior of the foundation
above grade.
- Control moisture – Maintain slope away from building as shown, carry
roof load of water at least three feet away from building, and make sure
that irrigation is directed away from the building.
- Chemical treatment – Use an environmentally-appropriate soil
treatment (such as Termidor®) and a building materials treatment (such
as Bora-Care®) for termite-prone near-grade wood materials.
- Inter-relationship of first three points – Since a builder and a
homeowner’s ability to employ or stick to each of the three strategies
above will vary, make sure that an inability to fully employ one
strategy is compensated for by complete rigor with the others. For
example, if for some reason, chemical treatment of soil or building
materials is not an option, then complete rigor in moisture control and
ground cover is required.
- Landscaping for wildfire control – keeping woody materials of
any type, living or otherwise, away from the building is good practice in
dry climates where wildfire presents a significant risk.
Field Experience Notes
- HVAC commissioning – The most efficient equipment means little
if the system is not set up and started up properly. Follow
high performance start-up procedures. In dry climates, it is generally
a good idea to set up the air distribution fan to run a little longer at
the end of each cycle to bump up the sensible efficiency.

Figure 16 |
- Energy trusses – There are a number of different truss
configurations that yield greater depth at the heel, but they vary quite a
bit in cost. The truss shown in Figure 16 (sometimes called a
“slider” truss) has proven to be among the most cost-competitive. And of
course, the pitch of the roof affects just how much insulation you can get
at this location, regardless of the type of truss.
- Advanced framing - For a technical resource that may help with
resistance to advanced framing methods from local code officials, see the
Building Safety Journal article written by Nathan Yost of BSC.
- Slabs – In dry climates, it is quite common for builders to use
a sand layer in between the polyethylene sheet and the cast concrete to
prevent differential drying and cracking problems. This moisture-holding
layer should never be placed between the poly and concrete. Differential
drying and subsequent cracking should be handled with a low water content
concrete and wetted burlap covering. See this
technical resource for more information.

Figure 17 |
- Single story homes and unvented/conditioned attics – Keeping
all ducts and HVAC equipment in conditioned space with slab-on-grade,
single story homes can be accomplished by moving the thermal barrier and
air barrier up to the roof line, making the attic an unvented, conditioned
space (see Figure 17). Below are the associated building science
points to consider when making the change to an unvented roof/conditioned
attic:
- Air sealing details – Unvented assemblies — walls or roofs — are
robust when the air sealing is robust. The hardest spots are not the
fields but the margins/edges of assemblies. Spray foam applied at the
margins (truss/rafter end blocking) may seem more expensive than cutting
in air stops and caulking between each truss or rafter, but the labor
savings and air sealing quality of spray foam are clear.
- Cavity insulation - Cellulose netting or fiberglass batt supports
create the insulation “belly” and accommodate cavity fill depth that
exceeds the depth of the truss top chord.
- Local acceptance - This assembly may require discussion with the
local building code official. See our
Unvented Roof Summary Article for assistance.
- HVAC configuration – See Figure 15 Interior Closet Configuration for
the basic HVAC setup in this structure.
- Moving this assembly to Mixed-Dry Climates – If an unvented
roof/conditioned attic assembly is employed where the coldest monthly
average temperature drops below 45°F, we recommend that a rigid
insulation be added exterior to the structural roof deck to warm the
assembly to the interior of the rigid insulation, thereby reducing the
potential for condensation problems in the structural roof deck. See
Figure 18 and the following technical resource for more information:
“Insulations, Sheathings, and
Vapor Diffusion Retarders.

Figure 18 |
- Tile roof – Tile roofs perform particularly well in this
climate, in terms of heat rejection. See
Energy Star Roof Product List for more information on roof tile with
high emissivity and high reflectivity, particularly important with
unvented, conditioned attics.
Material Compatibility and Substitutions
- Interior latex paint - The substitution of low permeability
interior finishes (vinyl wall paper, oil-based paints) for latex paint is
strongly discouraged as drying to the interior is important in mixed
climates.
- Exterior sheathing materials – In the second story of this
assembly, the reservoir cladding means that a moisture sensitive material
such as fiberboard should not be used. On the other hand, the lack of
cavity-warming exterior insulation means that an impermeable sheathing
such as thin-profile structural sheathing (e.g. Thermo-Ply®, Energy Brace)
should not be used. Plywood is an acceptable substitution for OSB in this
wall assembly. For more information, see the
Building Materials Property
Table or “Insulations,
Sheathings, and Vapor Diffusion Retarders."
- Cavity insulation materials – Acceptable cavity insulation
includes any that have a relatively high vapor permeability—cellulose,
fiberglass, foam (as long as air sealing is accomplished by a separate
component or system when cellulose or fiberglass is used). User discretion
can be based on properties other than building science.
- Flooring - Because curing concrete releases significant
moisture for several months after being cast, we recommend that a low w/c
concrete ratio (≤ 0.45) be used to protect the integrity of finished
flooring. We recommend that vinyl flooring not be installed over a
concrete slab. • Gypsum wallboard –Areas of potentially high moisture,
such as bathrooms, basements, and kitchens, are excellent candidates for
non-paper faced wallboard systems (e.g. James Hardie’s Hardibacker™, GP’s DensArmor™, USG’s Fiberock™). In addition, paper-faced gypsum board should
never be used as interior sheathing or backer for tub or shower surrounds
where ceramic tile or marble (any material with joints or grout lines) is
used as the finish.
- HVAC – A hot water-to-air coil in an air handling unit can be
used to replace the gas furnace hat exchanger. The coil can be connected
to a standard gas water heater with a draft hood located in the garage,
outside the conditioned space. Alternatively, the gas water heater can be
sealed combustion (or power-vented) and located within the conditioned
space. However, before you make this change, be sure to read the following
technical resource: “Combo
Space/Water Heating Systems – “Duo Diligence."
|
|